BCW1

PROGRESSIVE REPORT AS OF NOVEMBER 2024

Actual58. 6% 
Schedule57.5 % 
Slippage(+) 1.1 
Work Progress
BCW1 58.6%

Bridge Replacement Works

In spite of the considerable amount of preliminary works being executed on site, tranche 2 is yet to fully complete a new bridge as of this reporting period. Seven (7) bridges under BCW 2 have prepared the substructure and are waiting for the steel beam girders to arrive from China before they can construct the superstructure. Shipment for these bridges are expected in April 2024. We may witness the first few bridges to be completed and opened to traffic in May or June this year

DESIGN PROGRESS

BCW2

PROGRESSIVE REPORT AS OF NOVEMBER 2024

Actual67.52% 
Schedule65.41 % 
Slippage(+) 2.11 
Work Progress
BCW1 67.52%

BCW3

PROGRESSIVE REPORT AS OF MARCH 2024

 

Actual47.7 % 
Schedule61.8 % 
Slippage(-)14.1% 
Work Progress
BCW1 47.7%