Contract | Contractor/ Consultant | Commencement Date | Contract Amount | Duration | Completion Date |
Bridge Civil Works 1 (BCW 1) 35 Bridges | Metallurgical Corporation of China Ltd. (MCC) | 17-Oct-22 | PGK 315,395,676.88 | 1,095 | 16-Oct-25 |
days | |||||
Bridge Civil Works 2 (BCW 2) 19 Bridges | China Wu Yi Co. Ltd. (CWYC) | 17-Oct-22 | PGK 243,358,407.03 | 1,095 | 16-Oct-25 |
days | |||||
Bridge Civil Works 3 (BCW 3) 17 Bridges | China Civil Engineering Construction Corporation Ltd. (CCECC) | 31-Mar-23 | PGK 357,707,899.04 | 1,095 | 30-Mar-26 |
days | |||||
Consultancy Services 1 (CS 1) for BCW 1 | Korea Consultants International Co. Ltd. | 27-Jul-22 | USD 7,369,900 | 60 mos. | 26-Jul-27 |
PGK 13,509,420 | |||||
Consultancy Services 2 (CS 2) for BCW 2 | Bonifica | 12-Aug-22 | USD 9,980,200 | 60 mos. | 11-Aug-27 |
PGK 19,360,000 | |||||
Consultancy Services (BAMS 1) | Finnish Overseas Consultants Ltd. (FinnOC) | 27-Jul-22 | USD 9,648,370.50 | 24 mos. | 26-Jul-24 |
Total | PGK 1,018,143,614.45 |