Contract

Contractor/ Consultant

Commence Date

Amount

(PGK m)

Duration

Completion

Date

Amount

(PGK m)

 

Civil Works (CW1)

Nadzab Turn-off

to Henganofi Bridge (210 km)

Metallurgical Corporation of China Ltd. (MCC)

1-Feb-19

229.24

1446

days

17-Jan-23

324.06

 

Civil Works (CW2)

Henganofi Bridge to Mangiro Bridge & Miunde Bridge to Kagamuga Turn-off (161 km)

China Wu Yi Co., Ltd. (CWYC)

2-Feb-19

156.29

1446

days

18-Jan-23

273.26

 

Civil Works (RIC) Mangiro Bridge to Miunde Bridge (57 km)

China Harbor Engineering Co., Ltd. (CHEC)

2-Feb-19

170.65

1446

days

18-Jan-23

341.30

 

Supervision Consultancy (CS1) for CW1

Joint Venture led by Pyunghwa Engineering Consultants Ltd. (PEC)

11-Dec-18

36.14

46

months

10-Oct-22

48.14

 

Supervision Consultancy (CS2) for CW2 & RIC

Joint Venture led by Bonifica S.p.A

11-Dec-18

67.42

46

months

10-Oct-22

91.03

 

PMO Building

Construction

Zenith Ltd.

10-Dec-18

4.49

365 days

10-Dec-19

4.49

 

TOTAL

 

 

664.22

 

 

1,082.28